The first batch of Harpoon missiles purchased from the US would be delivered around the end of this year to provide critical combat power for the Littoral Combatant Command (LCC), the navy said yesterday.
Following the establishment of the LCC on Jan. 1, the first batch of the 400 Harpoon anti-ship missiles would be delivered around the end of this year on schedule, navy Chief of Staff Vice Admiral Chiu Chun-jung (邱俊榮) told a meeting of the legislature’s Foreign Affairs and National Defense Committee.
The LCC is thus expected to start operating in July next year, he said, adding that the navy would collaborate with the Ministry of National Defense to facilitate the adoption of the missiles, which would be critical combat equipment under the LCC’s jurisdiction.
Photo: Chen Yi-kuan, Taipei Times
Drones and uncrewed vessels would also be incorporated into the LCC system for littoral strikes and multidomain interception, he said, adding that their manufacturing has started.
Asked whether the timeline for the completion of the indigenous Hai Kun (海鯤) submarine was “overly optimistic,” Chiu agreed the initially planned six months for the testing phase was insufficient.
However, he added that he was confident they would be able to complete the test launch of training torpedoes from the submarine before the torpedo verification system leased from the US expires in May next year.
The submarine was built on schedule, but more time is needed for the testing, Chiu said, adding that all the equipment test reports met the navy’s criteria.
Minister of National Defense Wellington Koo (顧立雄) said that real-world challenges, such as difficulties in obtaining relevant equipment and technical support from the original manufacturer, were not fully understood when the timeline was set.
However, safety and quality would be prioritized in subsequent sea acceptance tests, he said.
Asked whether the Hai Kun uses a main engine typically for trucks or buses, Chiu said the designer of the engine and power source went through a selection process and has an export license.
CSBC Corp, Taiwan (台船) chairman Chen Cheng-hung (陳政宏) added that the engine was manufactured by a diesel-engine powerhouse, and that it would submit supporting documents to the legislature.
Asked whether penalties would be meted out if the submarine cannot be delivered to the navy next month as scheduled, Koo and the ministry’s Procurement Office Director Chao Ya-ping (趙亞平) said the daily fine would be about NT$190,000 (US$6,199).
The accumulated amount would be capped at about NT$4 billion, 20 percent of the NT$19.3 billion cost for building the submarine, they said.
Asked whether the verification equipment for the torpedo test must be returned to the US even if the test launch fails to be completed by May, Chiu said the navy would do its best to meet the goal.
It would apply to extend the lease period if needed, he said, adding that whether the equipment must be returned to the US could be negotiated.
A signaling system malfunction disrupted high-speed rail (HSR) services beginning at 8am today, with trains temporarily reduced to three northbound and three southbound trains per hour as authorities conduct inspections. The malfunction occurred on a section of track in Miaoli County during pre-operation checks early this morning, forcing northbound and southbound trains to use a single track, the HSR operator said. The regular schedule has been replaced with three hourly trains offering only nonreserved seating in each direction, stopping at every station, it said, adding that business class cars would still have reserved seating. Departures from terminal stations are scheduled at the top
‘NO SECURITY RISK’: The Railway Bureau reassured the public that the technicians’ activities were limited to technical guidance and did not involve sensitive systems The Railway Bureau yesterday said it had invited eight Chinese technicians to assist with an airport MRT construction project. The bureau issued the confirmation after an Internet user said Chinese nationals had entered the construction zone of Taiwan Taoyuan International Airport’s Terminal 3 project. They asked why “individuals from an enemy state” were allowed access to such a major national infrastructure project, which raised serious concerns over Taiwan’s industrial safety, sensitive systems and information security. The bureau’s Northern Region Engineering Branch Office said subcontractor Taiwan Handle Industrial Co (台灣手把工業) of the Taoyuan airport MRT’s “Contract No. CU05 Project A14 Station Civil, MEP &
Taiwan is still in the process of assessing the possibility of recruiting workers from Eswatini, the Ministry of Foreign Affairs said yesterday, adding that its goal is to help Eswatini upgrade its vocational training centers. If there are plans to recruit workers from Eswatini, safeguarding national security, protecting public health and ensuring the employment rights of Taiwanese would be prerequisites, Department of West Asian and African Affairs Director-General Yen Chia-liang (顏嘉良) told a news conference. Key considerations would also include filling labor shortages in specific industries, and fostering bilateral professional and technical exchanges, he said. Yen was asked about the progress of labor
A US uncrewed surface vessel (USV) encountered multiple Chinese warships during an autonomous transit of the Taiwan Strait, US defense company Seasats said in a statement on Wednesday. Seasats announced that a Lightfish USV had completed the first autonomous transit of the Taiwan Strait. Over five days, the USV traversed the entire length of the Strait while constantly monitoring surface vessel traffic, the company said. The Lightfish encountered multiple Chinese warships, one of which was a Chinese People’s Liberation Army Navy (PLAN) Type 056 corvette, it said. The Chinese vessels were operating “well within Taiwan’s exclusive economic zone without transmitting their identity via the