In the rolling hills of South Africa’s Mpumalanga province, hundreds of builders, welders and engineers are putting the final touches to a gigantic new power station that is set to burn as much as 13.6 million metric tonnes of coal a year until it is eventually shuttered in 2073.
The 4,800 megawatt, dry-cooled Kusile plant and the almost identical Medupi facility, which was completed last year, would be key to meeting demand for energy in a country that has been plagued by rolling blackouts since 2008.
However, environmentalists caution that their continued operation would be a major impediment to South Africa meeting its commitment to eliminating greenhouse gas emissions on a net basis by 2050.
Illustration: Mountain People
“It absolutely doesn’t make any sense to invest in mega coal-fired power stations in the face of a climate crisis when we should be focusing on a just transition to renewable energy,” said Melita Steele, interim program director for Greenpeace Africa, whose members chained themselves to Kusile’s entrance gates more than a decade ago to try and halt its construction.
Kusile and Medupi, owned by state power utility Eskom Holdings SOC Ltd, have been plagued by labor unrest, mismanagement and equipment defects from the outset, resulting in a succession of delays that have exacerbated electricity shortages. Both plants were approved in 2007 and were scheduled to be completed within eight years at a total cost of 163 billion rand (US$9.6 billion). The likely final price tag has since ballooned to about 464 billion rand, including interest costs during construction.
Meanwhile, Eskom has accumulated 396 billion rand of debt, stemming mainly from its funding of the new generating capacity, and it depends on state bailouts to survive, because it does not generate enough income to cover its operating and interest costs. Decommissioning its two newest plants early or pulling the plug on Kusile’s last units due to become commercially operational by 2024 would add to its financial woes, and it would in all likelihood fall to the government to make up for any forfeited revenue.
“Most of the work is done,” and Kusile’s limited output is already benefiting the country, Zandi Shange, Eskom’s general manager for projects, said on a tour of the plant near the town of Delmas, about 107km east of Johannesburg, as beeping trucks offloaded coal behind her.
Almost 20,000 workers were employed at the plant at the peak of the construction period, but that number has fallen by more than three-quarters as the last of its six units near completion, she said.
While Kusile, which means “the dawn has come” in the Ndebele and Siswati languages, is the country’s first plant to be fitted with a flue gas desulfurization unit that reduces its sulfur dioxide output, Greenpeace and other environmental rights groups have estimated that it would still emit 33.4 million tonnes of carbon dioxide a year.
It would also produce vast quantities of ash, mounds of which were seen piled up next to the plant.
Eskom said its license only requires it to report on particle emissions, sulfur dioxide and nitrogen oxide, and it does not have other accurate figures.
Coal would be trucked to Kusile until supply contracts that have been under negotiation with nearby mines since 2008 are fully concluded, and then conveyor belts would be built to bring it in directly, said Snehal Nagar, acting general manager for the utility’s primary energy division.
South Africa is the world’s 13th-biggest emitter of greenhouse gases, with Eskom’s 15 coal-fired plants the leading contributors. Under an agreement announced at the COP26 climate talks in Glasgow, Scotland, in November last year, the US, the UK, Germany, France and the EU agreed to secure US$8.5 billion to help South Africa transition away from the fossil fuel and reduce its emissions.
South Africa’s 2019 energy blueprint — which is under review — envisions coal accounting for 59 percent of electricity output by 2030, down from more than 80 percent. About 18 gigawatts of Eskom’s older coal capacity is scheduled to be shut down by 2035, with Kusile and Medupi the only other remaining plants that use the fuel expected to still be operational by 2050.
While the government has taken measures to bolster the production of green energy by private producers, including relaxing licensing provisions, the process has been dogged by delays and legal disputes.
The South African National Energy Development Institute, a government research unit, estimates that more than three times the amount of renewable power generating capacity would need to be developed to replace retired coal plants.
Steele sees no option but to accelerate that process.
“We continue to maintain that Kusile shouldn’t be completed and if it is finalized, it absolutely can’t run for its expected lifespan,” she said. “We really need to be including these new coal-fired power stations in plans to phase out coal.”
The gutting of Voice of America (VOA) and Radio Free Asia (RFA) by US President Donald Trump’s administration poses a serious threat to the global voice of freedom, particularly for those living under authoritarian regimes such as China. The US — hailed as the model of liberal democracy — has the moral responsibility to uphold the values it champions. In undermining these institutions, the US risks diminishing its “soft power,” a pivotal pillar of its global influence. VOA Tibetan and RFA Tibetan played an enormous role in promoting the strong image of the US in and outside Tibet. On VOA Tibetan,
On a quiet lane in Taipei’s central Daan District (大安), an otherwise unremarkable high-rise is marked by a police guard and a tawdry A4 printout from the Ministry of Foreign Affairs indicating an “embassy area.” Keen observers would see the emblem of the Holy See, one of Taiwan’s 12 so-called “diplomatic allies.” Unlike Taipei’s other embassies and quasi-consulates, no national flag flies there, nor is there a plaque indicating what country’s embassy this is. Visitors hoping to sign a condolence book for the late Pope Francis would instead have to visit the Italian Trade Office, adjacent to Taipei 101. The death of
By now, most of Taiwan has heard Taipei Mayor Chiang Wan-an’s (蔣萬安) threats to initiate a vote of no confidence against the Cabinet. His rationale is that the Democratic Progressive Party (DPP)-led government’s investigation into alleged signature forgery in the Chinese Nationalist Party’s (KMT) recall campaign constitutes “political persecution.” I sincerely hope he goes through with it. The opposition currently holds a majority in the Legislative Yuan, so the initiation of a no-confidence motion and its passage should be entirely within reach. If Chiang truly believes that the government is overreaching, abusing its power and targeting political opponents — then
As the highest elected official in the nation’s capital, Taipei Mayor Chiang Wan-an (蔣萬安) is the Chinese Nationalist Party’s (KMT) candidate-in-waiting for a presidential bid. With the exception of Taichung Mayor Lu Shiow-yen (盧秀燕), Chiang is the most likely KMT figure to take over the mantle of the party leadership. All the other usual suspects, from Legislative Speaker Han Kuo-yu (韓國瑜) to New Taipei City Mayor Hou You-yi (侯友宜) to KMT Chairman Eric Chu (朱立倫) have already been rejected at the ballot box. Given such high expectations, Chiang should be demonstrating resolve, calm-headedness and political wisdom in how he faces tough