The National Expressway Engineering Bureau on Monday said it would terminate its contract with Kuo Teng Construction Co if it fails to speed up construction of Kinmen Bridge.
Work on the bridge connecting the main island of Greater Kinmen (大金門) and Lieyu (烈嶼), also known as Little Kinmen, began in 2013 after it had been a campaign promise in five presidential elections.
Kinmen residents say the bridge will probably never be completed because of failures to keep up with the construction schedule and a series of accidents at the site.
The bureau said it might have to change the contractor for a third time, adding that Kuo Teng Construction has been instructed to increase the number of workers and boost construction materials, as well as to use more and better machinery to build the bridge.
“The contractor failed to bring in partners that were equipped with better machinery for the project, even though it was facing a shortage of workers and construction materials and clearly lacks the ability to handle the project on its own,” the bureau said in a statement.
“The contractor had fallen behind the construction schedule by 16.07 percent as of last month, which shows that it has neither the ambition nor the determination to expedite the progress of the work,” the bureau added.
It said that it informed Kuo Teng Construction in February that delays to the bridge’s construction mean the firm was barred from bidding for government projects for one year, adding that at the time, it was behind schedule by about 10 percent.
The bureau on Wednesday last week said that work on the bridge was nearly 19 percent behind schedule.
Based on the delays in construction, Kuo Teng Construction was officially notified that it must address the problem within 30 days or face termination of its contract with the government, the bureau said, adding that another qualified contractor would be recruited through a public tender so that work could proceed.
The bridge was the focus of a question-and-answer session at a meeting of the legislature’s Transportation Committee.
Public Construction Commission Minister Wu Hong-mo (吳宏謀) was asked what the commission would do to improve the quality and efficiency of public projects.
“My understanding is that the contractor lacks the ability to carry out the construction in deep water and has problems fulfilling the terms of the contract,” he said, adding he would seek to resolve the problem.
Wu said that the problem with public construction work in Taiwan is that contractors that are incapable of fulfilling the contract are often hired.
The key lies in that most government agencies prefer to choose the bidders that offer the cheapest packages for public contracts, fearing that they would be held accountable if the public were to accuse them of wasting taxpayers’ money.
Wu said his top priority is to make sure government workers are not afraid to hire firms that present the most comprehensive bids, adding that the commission would lay out the types of projects to which this bidding method applies.
The information for each project would be made transparent, including information on contractors’ safety records, he added.
UNILATERAL MOVES: Officials have raised concerns that Beijing could try to exert economic control over Kinmen in a key development plan next year The Civil Aviation Administration (CAA) yesterday said that China has so far failed to provide any information about a new airport expected to open next year that is less than 10km from a Taiwanese airport, raising flight safety concerns. Xiamen Xiangan International Airport is only about 3km at its closest point from the islands in Kinmen County — the scene of on-off fighting during the Cold War — and construction work can be seen and heard clearly from the Taiwan side. In a written statement sent to Reuters, the CAA said that airports close to each other need detailed advanced
Tropical Storm Fung-Wong would likely strengthen into a typhoon later today as it continues moving westward across the Pacific before heading in Taiwan’s direction next week, the Central Weather Administration (CWA) said. As of 8am, Fung-Wong was about 2,190km east-southeast of Cape Oluanpi (鵝鑾鼻), Taiwan’s southernmost point, moving westward at 25kph and possibly accelerating to 31kph, CWA data showed. The tropical storm is currently over waters east of the Philippines and still far from Taiwan, CWA forecaster Tseng Chao-cheng (曾昭誠) said, adding that it could likely strengthen into a typhoon later in the day. It is forecast to reach the South China Sea
WEATHER Typhoon forming: CWA A tropical depression is expected to form into a typhoon as early as today, the Central Weather Administration (CWA) said yesterday, adding that the storm’s path remains uncertain. Before the weekend, it would move toward the Philippines, the agency said. Some time around Monday next week, it might reach a turning point, either veering north toward waters east of Taiwan or continuing westward across the Philippines, the CWA said. Meanwhile, the eye of Typhoon Kalmaegi was 1,310km south-southeast of Oluanpi (鵝鑾鼻), Taiwan’s southernmost point, as of 2am yesterday, it said. The storm is forecast to move through central
UNKNOWN TRAJECTORY: The storm could move in four possible directions, with the fourth option considered the most threatening to Taiwan, meteorologist Lin De-en said A soon-to-be-formed tropical storm east of the Philippines could begin affecting Taiwan on Wednesday next week, the Central Weather Administration (CWA) said yesterday. The storm, to be named Fung-wong (鳳凰), is forecast to approach Taiwan on Tuesday next week and could begin affecting the weather in Taiwan on Wednesday, CWA forecaster Huang En-hung (黃恩鴻) said, adding that its impact might be amplified by the combined effect with the northeast monsoon. As of 2pm yesterday, the system’s center was 2,800km southeast of Oluanbi (鵝鑾鼻). It was moving northwest at 18kph. Meteorologist Lin De-en (林得恩) on Facebook yesterday wrote that the would-be storm is surrounded by