Taiwan's first high-speed rail system will not start service at the end of next month as scheduled, as construction of its core mechanical and electrical system has fallen seriously behind schedule, the company managing the project said yesterday.
"We will announce the new timetable after a meticulous evaluation by our board members," said Ted Chia (
At the end of July, THSRC had completed 87.89 percent of the 345km track, 92 percent of station constructions and only 60.44 percent of the core mechanical and electrical system, which has become the major cause for the postponement, Chia said.
The core mechanical and electrical system may be completed only by September next year, according to a Chinese-language newspaper report. In addition, THSRC needs at least two months of trial operation and five months of inspection by the Taiwan High Speed Rail Bureau, under the Ministry of Transportation and Communications. As a result, the high-speed railway may only be launched 18 months after the originally planned date.
While demanding that the Japanese-led Taiwan Shinkansen Corp (TSC, 台灣新幹線) -- contractor for the core mechanical and electrical system's construction -- accelerate production, THSRC also plans to demand that the Japanese consortium abide by the terms of the contract. According to the contract, in the event of falling behind schedule, TSC would have to pay THSRC NT$200 million per day in compensation and to cover interest losses until the construction is completed, a Chinese-language news report said yesterday.
The report also said that TSC has proposed additional terms when THSRC requested it to speed up construction.
The consortium of seven Japanese companies -- Mitsubishi Heavy Industries Ltd, Toshiba Corp, Kawasaki Heavy Industries Ltd, Mitsui & Co, Mitsubishi Corp, Marubeni Corp and Sumitomo Corp -- won the contract for this project in 2000.
The report, citing company supervisor Huang Che-hung (
Chia yesterday confirmed that TSC made additional requests, but said the content of the contract and the terms should remain confidential. Chia declined to comment on the amount of NT$200 million compensation per day, saying the number is merely an estimate touted by the media.
He did not comment on suggestions in the report that the postponement was ultimately the product of a long-standing disagreement between THSRC and TSC over certain technical problems associated with the core mechanical and electrical system. He said that the two companies are negotiating a solution to these problems.
Jack Hsu (許俊逸), a deputy director general of the Bureau of High Speed Rail, said the bureau has not yet received THSRC's formal notice about the postponement. He said the company needs to absorb the losses incurred by the delay itself, since it is a build-operate-transfer project.
According to the contract, THSRC needs to return the transportation facility to the government 35 years after the contract was signed in July 1998, Hsu said.
THSRC previously estimated that it can show ticket revenue of about NT$130 million per day during the initial stages of operation. Since the project has been delayed, it means it will now take longer for the company to break even.
The high-speed railway passed a 200kph test drive at the end of last month and is likely to have a successful 300kph test next month, Chia said.
This project marks the first use of Japan's Shinkansen system outside that country as well as the first time Japanese bullet trains have been exported.
Real estate agent and property developer JSL Construction & Development Co (愛山林) led the average compensation rankings among companies listed on the Taiwan Stock Exchange (TWSE) last year, while contract chipmaker Taiwan Semiconductor Manufacturing Co (TSMC, 台積電) finished 14th. JSL Construction paid its employees total average compensation of NT$4.78 million (US$159,701), down 13.5 percent from a year earlier, but still ahead of the most profitable listed tech giants, including TSMC, TWSE data showed. Last year, the average compensation (which includes salary, overtime, bonuses and allowances) paid by TSMC rose 21.6 percent to reach about NT$3.33 million, lifting its ranking by 10 notches
SEASONAL WEAKNESS: The combined revenue of the top 10 foundries fell 5.4%, but rush orders and China’s subsidies partially offset slowing demand Taiwan Semiconductor Manufacturing Co (TSMC, 台積電) further solidified its dominance in the global wafer foundry business in the first quarter of this year, remaining far ahead of its closest rival, Samsung Electronics Co, TrendForce Corp (集邦科技) said yesterday. TSMC posted US$25.52 billion in sales in the January-to-March period, down 5 percent from the previous quarter, but its market share rose from 67.1 percent the previous quarter to 67.6 percent, TrendForce said in a report. While smartphone-related wafer shipments declined in the first quarter due to seasonal factors, solid demand for artificial intelligence (AI) and high-performance computing (HPC) devices and urgent TV-related orders
Prices of gasoline and diesel products at domestic fuel stations are this week to rise NT$0.2 and NT$0.3 per liter respectively, after international crude oil prices increased last week, CPC Corp, Taiwan (台灣中油) and Formosa Petrochemical Corp (台塑石化) said yesterday. International crude oil prices last week snapped a two-week losing streak as the geopolitical situation between Russia and Ukraine turned increasingly tense, CPC said in a statement. News that some oil production facilities in Alberta, Canada, were shut down due to wildfires and that US-Iran nuclear talks made no progress also helped push oil prices to a significant weekly gain, Formosa said
MINERAL DIPLOMACY: The Chinese commerce ministry said it approved applications for the export of rare earths in a move that could help ease US-China trade tensions Chinese Vice Premier He Lifeng (何立峰) is today to meet a US delegation for talks in the UK, Beijing announced on Saturday amid a fragile truce in the trade dispute between the two powers. He is to visit the UK from yesterday to Friday at the invitation of the British government, the Chinese Ministry of Foreign Affairs said in a statement. He and US representatives are to cochair the first meeting of the US-China economic and trade consultation mechanism, it said. US President Donald Trump on Friday announced that a new round of trade talks with China would start in London beginning today,