Government leaders are defending the reliability of Brazil’s power grid after a huge blackout left nearly 60 million people in the dark and raised concerns about its ability to guarantee electricity for a surging economy.
Energy Minister Edison Lobao said the hours-long blackout on Tuesday night was caused by heavy rain, lightning and strong winds that made transformers on a vital high-voltage transmission line short circuit, leading two other lines to go down as part of an automatic safety mechanism.
The massive Itaipu dam on the border with Paraguay — the world’s second-largest hydroelectric power producer — was completely shut down for the first time in its 25-year history during the blackout, but Loboa stressed the plant was not the problem.
“The problem was exclusively with the transmission lines,” he said on Wednesday.
The blackout cut electricity to 18 of Brazil’s 26 states and left them without power for up to four hours. About 7 million people also lost water service in Sao Paulo. All of Paraguay briefly lost power.
Analysts said the blackout shows Brazil’s lack of investment in the power system at a time when Latin America’s largest economy is booming and the country is preparing to host the 2014 World Cup and 2016 Olympics.
The Brazilian Olympic Committee would not comment on the power failure. But among guarantees made to the International Olympic Committee is that Rio, as the host city in 2016, will be isolated from the nation’s power system — to avoid problems like this. The city will have its own direct energy feed during the Games.
“There is an absolute failure of infrastructure in terms of energy,” said Patrizia Tomasi, an engineer with the Brazilian energy consulting firm Planck E.
“What we are seeing now is only the beginning. There is a need to invest more, to improve how energy is managed by those in the government. We have Itaipu, which is huge, which is great, but there are no lines to transmit all that energy.”
Brazilian President Luiz Inacio Lula da Silva disputed that the government has not done enough to improve the power grid since he took office in 2003, two years after Brazil suffered shortages and rationing under his predecessor.
“In seven years, we created 30 percent of all the transmission lines built in the last 130 years,” Silva said. “There was no shortage of power generation, and the problem was not a lack of transmission lines.”
Lobao said Silva’s government has invested about US$13 billion in transmission lines and US$4.7 billion more on transformers since 2003.
The energy minister also defended the strength of the Brazilian system — pointing out it took a day to fully restore power after a blackout hit the East Coast of the US and Canada in 2003, leaving 50 million people in the dark. He mentioned lengthier blackouts in other nations, including Italy and Japan.
It was at least the fourth time since 1985 that Brazil has suffered a mammoth power outage blamed on transmission line failures from Itaipu.
The worst of the blackouts occurred in 1999 after lightning struck a power substation in Sao Paulo state, plunging 97 million Brazilians into darkness for up to five hours.
After severe energy shortages and rationing in 2001, Brazil diversified its energy supply. It has seen blackouts since, but none like Tuesday’s failure, in which the power outage was more geographically widespread. Analysts say the scope of the blackout was so large because the nation’s power grid has become more interconnected, meaning a glitch in one part can affect a wider area.
The Philippines yesterday said its coast guard would acquire 40 fast patrol craft from France, with plans to deploy some of them in disputed areas of the South China Sea. The deal is the “largest so far single purchase” in Manila’s ongoing effort to modernize its coast guard, with deliveries set to start in four years, Philippine Coast Guard Commandant Admiral Ronnie Gil Gavan told a news conference. He declined to provide specifications for the vessels, which Manila said would cost 25.8 billion pesos (US$440 million), to be funded by development aid from the French government. He said some of the vessels would
CARGO PLANE VECTOR: Officials said they believe that attacks involving incendiary devices on planes was the work of Russia’s military intelligence agency the GRU Western security officials suspect Russian intelligence was behind a plot to put incendiary devices in packages on cargo planes headed to North America, including one that caught fire at a courier hub in Germany and another that ignited in a warehouse in England. Poland last month said that it had arrested four people suspected to be linked to a foreign intelligence operation that carried out sabotage and was searching for two others. Lithuania’s prosecutor general Nida Grunskiene on Tuesday said that there were an unspecified number of people detained in several countries, offering no elaboration. The events come as Western officials say
Hundreds of thousands of Guyana citizens living at home and abroad would receive a payout of about US$478 each after the country announced it was distributing its “mind-boggling” oil wealth. The grant of 100,000 Guyanese dollars would be available to any citizen of the South American country aged 18 and older with a valid passport or identification card. Guyanese citizens who normally live abroad would be eligible, but must be in Guyana to collect the payment. The payout was originally planned as a 200,000 Guyanese dollar grant for each household in the country, but was reframed after concerns that some citizens, including
A plane bringing Israeli soccer supporters home from Amsterdam landed at Israel’s Ben Gurion airport on Friday after a night of violence that Israeli and Dutch officials condemned as “anti-Semitic.” Dutch police said 62 arrests were made in connection with the violence, which erupted after a UEFA Europa League soccer tie between Amsterdam club Ajax and Maccabi Tel Aviv. Israeli flag carrier El Al said it was sending six planes to the Netherlands to bring the fans home, after the first flight carrying evacuees landed on Friday afternoon, the Israeli Airports Authority said. Israeli Prime Minister Benjamin Netanyahu also ordered