Columns of steam shoot from the ground at an Indonesian power plant sitting in the shadow of an active volcano, as energy is tapped from the red-hot underbelly of the archipelago.
Pipes zigzag up rugged mountainsides covered in tea plantations, carrying steam from the Earth’s core to power enormous turbines at the Wayang Windu facility on Java island, Indonesia.
Indonesia, a seismically-active island chain studded with scores of volcanoes, holds about 40 percent of the world’s geothermal energy reserves, but has long lagged behind in its use of the renewable power source.
Photo: AFP
Now the government is pushing to expand the sector five-fold in the next decade, although the challenges are huge in a country where the burden of red tape remains onerous, big projects are often delayed and targets missed.
“The potential is tremendous,” said Rully Wirawan, field manager at Wayang Windu. “The current [Indonesian] government is trying to tackle the challenges, so I believe the development of the sector will be better in future.”
Geothermal, a clean energy source which releases negligible amounts of greenhouse gases, unlike burning dirty fossil fuels, is mostly found in seismically-active areas around tectonic plate boundaries.
The Earth’s heat emanating through the fault lines warms underground reservoirs and the resulting steam can be channeled to geothermal energy plants.
Fossil fuel addiction
The majority of Indonesia’s power is generated from its abundant reserves of coal and oil. It has installed capacity to produce about 1,400 megawatts of electricity from geothermal, enough to provide power to just 1.4 million households in the country of 255 million.
That is less than 5 percent of geothermal’s estimated potential and behind the world’s two leading producers of the energy source, the US and the Philippines.
However, the Indonesian government is aiming to increase the country’s generating capacity to about 7,200 megawatts by 2025, as part of a broader plan to boost the renewables sector, which would likely make it the world’s top producer of the power source.
A major part of the drive is a law passed two years ago that means geothermal exploration is no longer considered mining activity, as it was previously. The old definition had held up the industry as mining cannot be carried out in the country’s vast tracts of protected forests, believed to contain about two-thirds of Indonesia’s geothermal reserves.
The Indonesian government is also seeking to sweeten local administrations — which had sometimes resisted the construction of the steam-belching facilities — by offering them up to 1 percent of revenue from any geothermal plant in their area.
Abadi Poernomo, chairman of the Indonesian Geothermal Association, which represents companies involved in the sector, is upbeat about future prospects: “A lot of investors from abroad are coming to Indonesia with the intent to develop geothermal.”
High costs, red tape
Still, the challenges are enormous. While achieving the 2025 target might be possible, it would be extremely difficult, said Daniel Wicaksana, an energy expert at consultancy Frost and Sullivan Indonesia.
One of the biggest problems is the high exploration costs needed at the outset, as checking for potential geothermal reserves is a complex, time-consuming business that is not always successful.
Building a geothermal plant costs the equivalent of between US$4 million and US$5 million dollars per megawatt, compared with US$1.5 million to US$2 million for a coal-fired power station, the association said.
Investors have also complained about what they say is the relatively low price offered by the state-run power company to buy electricity from a geothermal facility, which they claim usually does not cover the large initial outlay.
To top it all off, Indonesia’s complicated bureaucracy puts many off — 29 permits are required from different government agencies and ministries for a geothermal plant and time-consuming negotiations with powerful local administrations can also hamper progress.
“The level of complexity to complete the necessary paperwork, at the local level especially, also adds to the slow development of geothermal,” Wicaksana said.
“Green” groups have also questioned authorities’ commitment to geothermal in the near term — a plan by the Indonesian government to ramp up electricity producing capacity dramatically by 2019 seems more focused on building coal-fired power stations than expanding the use of renewable energy sources.
Wayang Windu, which is jointly managed by independent company Star Energy and state-owned energy giant Pertamina and takes its names from the active volcano near the plant, illustrates some of the challenges.
Exploration first began at the site in 1985, but it was not until 15 years later that the plant began producing electricity commercially, while work on a new unit to boost power generation has been delayed due to negotiations over cost.
Even officials admit achieving the Indonesian government’s geothermal target is likely to be tough.
Ego Syahrial, the head of the government’s geology agency, which assesses geothermal energy reserves conceded: “The progress is not very encouraging, to be honest.”
CONFRONTATION: The water cannon attack was the second this month on the Philippine supply boat ‘Unaizah May 4,’ after an incident on March 5 The China Coast Guard yesterday morning blocked a Philippine supply vessel and damaged it with water cannons near a reef off the Southeast Asian country, the Philippines said. The Philippine military released video of what it said was a nearly hour-long attack off the Second Thomas Shoal (Renai Shoal, 仁愛暗沙) in the contested South China Sea, where Chinese ships have unleashed water cannons and collided with Philippine vessels in similar standoffs in the past few months. The China Coast Guard and other vessels “once again harassed, blocked, deployed water cannons, and executed dangerous maneuvers” against a routine rotation and resupply mission to
GLOBAL COMBAT AIR PROGRAM: The potential purchasers would be limited to the 15 nations with which Tokyo has signed defense partnership and equipment transfer deals Japan’s Cabinet yesterday approved a plan to sell future next-generation fighter jets that it is developing with the UK and Italy to other nations, in the latest move away from the country’s post-World War II pacifist principles. The contentious decision to allow international arms sales is expected to help secure Japan’s role in the joint fighter jet project, and is part of a move to build up the Japanese arms industry and bolster its role in global security. The Cabinet also endorsed a revision to Japan’s arms equipment and technology transfer guidelines to allow coproduced lethal weapons to be sold to nations
Thousands of devotees, some in a state of trance, gathered at a Buddhist temple on the outskirts of Bangkok renowned for sacred tattoos known as Sak Yant, paying their respects to a revered monk who mastered the practice and seeking purification. The gathering at Wat Bang Phra Buddhist temple is part of a Thai Wai Khru ritual in which devotees pay homage to Luang Phor Pern, the temple’s formal abbot, who died in 2002. He had a reputation for refining and popularizing the temple’s Sak Yant tattoo style. The idea that tattoos confer magical powers has existed in many parts of Asia
ON ALERT: A Russian cruise missile crossed into Polish airspace for about 40 seconds, the Polish military said, adding that it is constantly monitoring the war to protect its airspace Ukraine’s capital, Kyiv, and the western region of Lviv early yesterday came under a “massive” Russian air attack, officials said, while a Russian cruise missile breached Polish airspace, the Polish military said. Russia and Ukraine have been engaged in a series of deadly aerial attacks, with yesterday’s strikes coming a day after the Russian military said it had seized the Ukrainian village of Ivanivske, west of Bakhmut. A militant attack on a Moscow concert hall on Friday that killed at least 133 people also became a new flash point between the two archrivals. “Explosions in the capital. Air defense is working. Do not