Mon, Sep 20, 2010 - Page 3 News List

INTERVIEW: Architect blames Palace Museum for lacking will

By Vincent Y. Chao  /  STAFF REPORTER

It was supposed to be one of southern Taiwan’s most ambitious building projects in years, a defining NT$6 billion (US$189 million) world-class museum that promised stunning modern architecture, storing tens of thousands of rare antique works of art and ancient treasures from throughout Asia.

Nearly a decade since it was first announced, Paul Fehlau, an executive senior associate at US-based Antoine Predock Architect (APA) and one of the former lead architects of the museum — the first branch of the National Palace Museum (NPM) outside Taipei — says it may never be completed.

“Looking back at the entire proposal, I’m not sure I can say that whether I really had the feeling that they were going to finish it,” he told the Taipei Times, referring to the museum’s administration.

“The main problem was a fundamental lack of attention in the project, a lack of belief in trying to get it finished,” he said. “Had they really wanted to get it finished, they would have finished it [long before].”

APA, a rapidly growing firm recently rated by Architectural ­Digest as one of the top 20 global designers, was selected from a field of six finalists as part of an international architectural contest for the project, first made public in 2001.

At the time, the firm said the mountain-shaped design would be an “approachable, celebratory community center, a fluid, living scroll, that is woven and read, felt and lived, as it travels back in time, spiraling and unfolding toward contemporary Taiwan and the future.”

However, fast-forward nine years and two project deadlines later and the 70 hectare site, located minutes from Chiayi High Speed Rail Station, remains nearly empty. It was recently revealed that the museum would now be pushed back to a 2017 opening, breaking a promise by President Ma Ying-jeou (馬英九) late last year for a spring 2012 opening, infuriating both county officials and tourism operators.

Last month, National Palace Museum Director Chou Kung-shin (周�? told the Taipei Times the delay resulted from problems with flooding in the area, as well as unresolved problems, including that the design was over budget with its two major contractors, APA and Lord Cultural Resources, one of the world’s ­largest museum management firms.

Both firms have filed lawsuits against the central government, accusing it of breaching the original contract.

Fehlau, who says the NPM southern branch was one of their first forays in Asia and the reason it entered the Taiwanese market, tells a different story. From the onset, he said, the NPM was never fully committed to the project, which was fraught with bureaucratic and budgetary delays.

“You know, they really only got serious about the project when the elections were coming up. That’s the thing that pushed it forward at each stage,” he said.

The lack of will also meant that the design firm was sporadically paid and later prevented from dealing directly with museum officials. Fehlau said that at one point the design firm was not paid for a full two years, while meetings with top museum officials were rebuffed and referred to another engineering subcontractor.

While the NPM claimed that the APA design exceeded its NT$3 billion budget for constructing the main building and that the firm ­refused requests for a revision, Fehlau said the NPM failed to provide a budget estimate until late in the design phase and refused to provide them with other essential data.