As the sun sets on California’s solar farms, a backup energy source deep in the Sierra Nevada Mountains springs to life.
The huge system of reservoirs and turbines can store energy during the day and then crank out electricity for 900,000 homes, using just water and gravity.
As the state tries to make wind and solar work around the clock, officials want to build more like it. It is not likely to not be easy: Such projects take years to develop, are expensive and face stiff opposition.
The push by California and other states to revive the century-old technology — called “pumped-hydro storage” — underscores the limitations of modern batteries. While utilities are aggressively installing lithium-ion systems on California’s grid, facilities such as the aging one in the Sierras can deliver far more electricity than anything made by Tesla Inc.
“It’s not as glamorous as a battery, but it’s a tried and true technology that provides the volume that we need,” said Neena Kuzmich, project manager for a proposed pumped-storage facility near San Diego.
California’s goal to get 100 percent of its electricity from carbon-free sources by 2045 requires an unprecedented amount of energy storage.
Lithium-ion battery installations produce a few hundred megawatts of electricity at most. The 35-year-old plant in the Sierras — PG&E Corp’s Helms Pumped Storage facility — can deliver more than 1,200 megawatts at a clip.
The Swiss pioneered pumped-storage technology in the late 1800s, but it did not take off in the US until the 1960s and 1970s, when dozens of plants were built to store surplus energy from nuclear reactors and other big plants. There are seven in California alone.
Renewed interest is surging. The US Federal Energy Regulatory Commission has issued 34 preliminary permits for companies and government agencies exploring projects in New York, Pennsylvania, Wyoming and elsewhere. Another 16 applications are pending. Nine are proposed in California.
The idea is simple. Take two reservoirs at different elevations, connected by pipes or tunnels. When electricity is abundant, pump water from the lower reservoir to the one uphill. When the grid needs power, let the water flow back down through turbines.
While the concept is straightforward, execution is not. The projects can cost more than US$1 billion to build. They are cheap once up and running, but the huge upfront price makes them more expensive overall than utility-scale batteries, according to BloombergNEF.
Plus, securing permits, building dams and boring tunnels can take 10 years, and since the process often involves flooding valleys, most projects face resistance.
That is particularly true in California. Environmentalists there have scrutinized pumped storage projects not just for their effect on the wilderness — but for using too much water, too.
The furthest along of the projects proposed in the state would be next to Joshua Tree National Park, using abandoned mining pits for reservoirs. It has met fierce opposition.
“It would be drawing extraordinary amounts of water from an aquifer that feeds essentially everything in the park,” said Kathryn Phillips, Sierra Club director for California.
A spokesman for NextEra Energy Inc, which bought a majority interest in the project last year, said environmental impacts were thoroughly vetted before federal regulators approved it in 2014. Construction has yet to begin.
Other projects would incorporate existing reservoirs.
The Los Angeles Department of Water and Power has proposed converting the Hoover Dam into a giant pumped-storage facility, and the San Diego County Water Authority wants to build a reservoir uphill from an existing one to create a storage system.
Start-up Oceanus Power & Water, meanwhile, has applied for federal permits to study two spots on the coast for systems to store energy and desalinate seawater. They would pump ocean water up to a reservoir. The water would then flow back down, with some diverted into a system to remove the salt. The rest would power turbines.
“Anywhere there’s a large coastal population in a semi-arid part of the world, our solution can work,” Oceanus chief executive officer Neal Aronson said.
DECOUPLING? In a sign of deeper US-China technology decoupling, Apple has held initial talks about using Baidu’s generative AI technology in its iPhones, the Wall Street Journal said China has introduced guidelines to phase out US microprocessors from Intel Corp and Advanced Micro Devices Inc (AMD) from government PCs and servers, the Financial Times reported yesterday. The procurement guidance also seeks to sideline Microsoft Corp’s Windows operating system and foreign-made database software in favor of domestic options, the report said. Chinese officials have begun following the guidelines, which were unveiled in December last year, the report said. They order government agencies above the township level to include criteria requiring “safe and reliable” processors and operating systems when making purchases, the newspaper said. The US has been aiming to boost domestic semiconductor
Nvidia Corp earned its US$2.2 trillion market cap by producing artificial intelligence (AI) chips that have become the lifeblood powering the new era of generative AI developers from start-ups to Microsoft Corp, OpenAI and Google parent Alphabet Inc. Almost as important to its hardware is the company’s nearly 20 years’ worth of computer code, which helps make competition with the company nearly impossible. More than 4 million global developers rely on Nvidia’s CUDA software platform to build AI and other apps. Now a coalition of tech companies that includes Qualcomm Inc, Google and Intel Corp plans to loosen Nvidia’s chokehold by going
ENERGY IMPACT: The electricity rate hike is expected to add about NT$4 billion to TSMC’s electricity bill a year and cut its annual earnings per share by about NT$0.154 Taiwan Semiconductor Manufacturing Co (TSMC, 台積電) has left its long-term gross margin target unchanged despite the government deciding on Friday to raise electricity rates. One of the heaviest power consuming manufacturers in Taiwan, TSMC said it always respects the government’s energy policy and would continue to operate its fabs by making efforts in energy conservation. The chipmaker said it has left a long-term goal of more than 53 percent in gross margin unchanged. The Ministry of Economic Affairs concluded a power rate evaluation meeting on Friday, announcing electricity tariffs would go up by 11 percent on average to about NT$3.4518 per kilowatt-hour (kWh)
OPENING ADDRESS: The CEO is to give a speech on the future of high-performance computing and artificial intelligence at the trade show’s opening on June 3, TAITRA said Advanced Micro Devices Inc (AMD) chairperson and chief executive officer Lisa Su (蘇姿丰) is to deliver the opening keynote speech at Computex Taipei this year, the event’s organizer said in a statement yesterday. Su is to give a speech on the future of high-performance computing (HPC) in the artificial intelligence (AI) era to open Computex, one of the world’s largest computer and technology trade events, at 9:30am on June 3, the Taiwan External Trade Development Council (TAITRA) said. Su is to explore how AMD and the company’s strategic technology partners are pushing the limits of AI and HPC, from data centers to